Building a Saltwater Swimming Pool in Apollo Beach, FL: From Signed Contract to Finished Pool
- By Creative Pool & Spa
- Apollo Beach, FL 33572
About This Project
- New Gunite Pool
- Salt System
- Glass Waterline Tile
- Paver Deck
- Aluminum Railing
- Fencing
See the Transformation
Drag the handle to compare the space before and after.


The Starting Point
The homeowners wanted a pool made for swimming. We recommended a simple rectangular pool and left out a sun shelf to leave more room to swim, with depths running from 3′6″ to 5′6″.
Our first design was a larger pool. To bring the budget down, we resized it, then shifted it about five feet toward the center of the house so it sits balanced against the home.
What We Did
Finish and tile: For the interior, the homeowners chose a Diamond Brite “Super Blue” finish with Luvtile glass tile at the waterline.
Equipment built for the location: We swapped the originally specified chlorine feeder for a salt system at the homeowners’ request. The pump and filter sit on an elevated stand, and the deck is set slightly above grade on deeper footers. Both were precautions taken with the area’s storm flooding in mind, after the HOA cautioned about pools that had flooded in past storms.
Deck and safety: About 605 square feet of paver deck with coping surrounds the pool, with aluminum railing and a perimeter fence with two gates.
Project Details
- Pool
- New gunite, about 331 sq ft of water surface, ~10,600 gallons, 3′6″ to 5′6″ depth, rectangular
- Interior finish
- Diamond Brite “Super Blue” with Luvtile glass waterline tile
- Sanitation
- Salt chlorination system
- Equipment
- Pentair pump and Pentair Clean & Clear Plus cartridge filter on an elevated equipment stand
- Lighting
- Pentair MicroBrite color LED light
- Deck & safety
- ~605 sq ft paver deck with coping, aluminum railing, perimeter fence with two gates
The Finished Project
The Real Timeline
- June 2026: Design finalized and contract signed (June 24), right after HOA approval.
- July 2026: Pool engineering completed, with signed drawings issued late in the month.
- August 6, 2026: Building permit issued.
- August 24 – September 26, 2026: Construction, about five weeks from dig to finished pool.
- October 2026: Project completed.
During planning we estimated about a month for engineering, a month for permitting and roughly six weeks of construction after HOA approval. Construction itself finished in about five weeks.
How long does it take to build a pool in Apollo Beach?
For this pool, engineering and permitting took about six weeks after the contract was signed, and construction took about five weeks (August 24 to September 26, 2026). Every project’s timeline depends on HOA review, engineering and permitting.
Thinking about a pool of your own? Read how our new pool construction process works, or visit our Tampa pool builders and Brandon pool builders pages for projects around Tampa Bay. Creative Pool & Spa also resurfaces existing pools across Southwest and Central Florida.
To see every construction stage of a larger pool-and-spa build, follow our Venice gunite pool and spa construction from excavation to finished water.
Read how this pool was planned around HOA approval and storm-flood concerns on Creative Outdoor Florida.
Client Review
“No guessing what or when each step would occur. [...] His schedule and time to completion was 100% on time...and in some cases ahead of schedule.”